120711 UPDATE
120711 UPDATE
117 Hogue Rd: currently built through HVAC, rough electrical starts 7/16
123 Blackjack Drive: scheduled up to customer HS, I wont schedule any further until the customer completes all their work
13 Shannon Rd: working through the deck stain issue
185 Nevada Place: complete, drying out crawl space but the house is done and they live there
201 Sparrow Lane: final inspect tmrrw, should be done by the end of next week
2045 44th Ave: waiting for CCBP to respond regarding the fire penetrations, then onto insulation
221 N. Bodine Rd: everything complete to combo, called for tmrrw, possibly insulate next week
222 Canvasback Dr: complete with minor punchout
311 Riley Court: minor punchout such as electrical, etc. See list.
362 Boundary Rd: couple combo corrections, start hanging Monday possibly
370 Silver Shores Dr: waiting to hear back from CCBP on truss revision
464 Leudinghaus Rd: punchout items, hope to be complete by next Friday
56 Blacktail Ridge: need to install door to den
600 Alroy Lane: rough electrical schd to start today, combo next week
2504 32nd Ave: dug out today, ready to pour foundation
3016 Pershing Way: waiting for customer to complete concrete polishing, then framing