117 Hogue Rd: i know nothing

123 Blackjack Drive: scheduled up to customer HS, I wont schedule any further until the customer completes all their work

13 Shannon Rd: final inspection has passed and walkthrough is 5/7

185 Nevada Place: job is scheduled to completion, customer is in good spirits at this point

201 Sparrow Lane: combo inspection schd for next week

2045 44th Ave:  schedueld to combo inspection

221 N. Bodine Rd: foundation complete today and utilities and backfill to occur the beginning of next week.  Framing to start possibly the week after.

222 Canvasback Dr: scheduled to customers hardsurfaces, will schedule to completion after confirmation they are complete

311 Riley Court: flushing today, possibly texture next week, need to schedule to completion***

362 Boundary Rd: plumbing 5/14, working on schd***

370 Silver Shores Dr: schd to combo, need Doug to return

464 Leudinghaus Rd:mudding and taping, working up schedule

56 Blacktail Ridge: final inspection passed, working up trim schedule

600 Alroy Lane: framing starting 5/10

XXX Pershing Ave: permitting